Easy to use certification guide for 70-178 - Microsoft Project 2010, Managing Projects
In addition to ensuring that you are provided with only the best and most updated 70-178 guide torrent materials, we assure you to be able to access them easily, whenever you want. For PDF version everyone knows its use methods. As for PC Test Engine and Online Test Engine we have use guide or online help. Certification guide for 70-178 - Microsoft Project 2010, Managing Projects will help you pass exam successfully.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
We provide the most accurate 70-178 guide torrent materials
As a professional IT exam torrent provider, GuideTorrent.com gives you more than just certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam. We provide our users with the most accurate study guide PDF and the guarantee of pass. We assist you to prepare easily before the real test which are regarded valuable the IT sector. You can easily find three versions of the best valid 70-178 guide torrent: PDF version, PC Test Engine and Online Test Engine.
We provide you 100% money back guarantee
We guarantee your success at your first attempt with our certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam. If you do not pass the exam at your first try with our study guide materials, we will give you a full refund as soon as possible.
We provide you 7*24 online assistant
We provide you with 7*24 customer service to assistant. You can contact us when you need help with our certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam or any problems about the IT certification exams. We are ready to help you at any time.
We support you excellent and reliable after-sale service for you
Our relationship with you doesn't begin and end with you monetary transaction with us about certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam. In case you have issues in finding or using our exam torrent or something about Microsoft Microsoft Project certifications, our friendly support staff will assist you promptly whenever you contact us.
Microsoft Project 2010, Managing Projects 70-178 guide torrent materials
As professional elites in the Information Technology industry many candidates know if you can pass Microsoft exams and obtain Microsoft Project certifications your career development will be a new high lever. If you don't want to waste too much time and energy on the exam preparation, our certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam will be your right choice. As we all know the passing rate is really low and the exam cost is expensive, if you fail once and you need to pay much attention and twice or more exam cost, purchasing our 70-178 guide torrent materials can help you pass exams at first shot. You will only spend a little money and 15-36 hours on our study guide materials, our certification guide for 70-178 - Microsoft Project 2010, Managing Projects helps you save a lot of time, money and energy.
We provide Credit Card payment with credit card
Credit Card is the faster, safer way to send money, make an online payment, receive money or set up a merchant account in international trade. Our Certification guide for 70-178 - Microsoft Project 2010, Managing Projects exam is easy to purchase. Also if buyers want to refund, Credit Card also is convenient for users.
Microsoft 70-178 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Creating a Project Plan | 20% | - Initialize a project
|
| Topic 2: Tracking and Controlling Projects | 25% | - Update progress and schedule
|
| Topic 3: Configuring and Automating Projects | 10% | - Customize Project 2010 environment
|
| Topic 4: Viewing and Reporting Project Data | 20% | - Customize views and tables
|
| Topic 5: Managing Resources and Assignments | 25% | - Create and configure resources
|
Microsoft Project 2010, Managing Projects Sample Questions:
Question 1
Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
A. In the Resource Information window for John, change John's availability by modifying the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100 percent.
B. Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.
C. In the Resource Information window for John, select the inactive option for Thursday and cancel the selection of the inactive option for Saturday.
D. Update the project calendar for John by making Thursday as a non-working day and Saturday as a working day.
Question 2
You update your project schedule based on information received from your team members in today's status meeting. You need to compare the current revised project schedule with the baseline schedule side by side. Which default view should you use?
A. Calendar
B. Leveling Gantt
C. Multiple Baselines Gantt
D. Tracking Gantt
E. Timeline
Question 3
You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
A. Apply the Late Tasks filter.
B. Apply the Incomplete Tasks filter.
C. Apply the Status group.
D. Apply the Priority group.
E. Apply the Critical Tasks filter.
Question 4
You add a new summary task and detailed tasks to an existing project. You save the changes as Baseline2. You discover that Baseline2 only displays work hours for detailed tasks. You need to ensure that Baselinez displays work hours in the new summary task. What should you do?
A. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
B. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Entire project radio button, and then click OK.
C. ?Highlight the new detailed tasks. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, and then click OK.
D. ?Highlight the new summary task. ?Click Set Baseline and select Baseline2. ?Click the Selected tasks radio button, select From Subtasks into selected summary task(s), and then click OK.
Question 5
You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A. Click the Insert Milestone button.
B. Select the Mark Task as Milestone check box.
C. Change Work to zero hours.
D. Remove the predecessor assignments.
Solutions:
| Question 1 Answer: B | Question 2 Answer: D | Question 3 Answer: E | Question 4 Answer: D | Question 5 Answer: B |