[Nov-2021] Dumps Practice Exam Questions Study Guide for the C_TS422_2020 Exam C_TS422_2020 Dumps with Practice Exam Questions Answers SAP C_TS422_2020 Exam Syllabus Topics: TopicDetailsTopic 1Select and apply planning strategies, use the planning table, characterize long-term planningDetermine master data objects for process ordersTopic 2Introduction to SAP S/4HANA Supply Chain PlanningIdentify features [...]

[Nov-2021] Dumps Practice Exam Questions Study Guide for the C_TS422_2020 Exam [Q14-Q35]

Share

[Nov-2021] Dumps Practice Exam Questions Study Guide for the C_TS422_2020 Exam

C_TS422_2020 Dumps with Practice Exam Questions Answers


SAP C_TS422_2020 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Select and apply planning strategies, use the planning table, characterize long-term planning
  • Determine master data objects for process orders
Topic 2
  • Introduction to SAP S/4HANA Supply Chain Planning
  • Identify features for Good Manufacturing Practices (GMP)
Topic 3
  • Outline production planning components and functions, differentiate consumption-based planning vs. MRP
  • Identify repetitive manufacturing specific master data
Topic 4
  • Characterize process order elements and process order processing
  • Outline the basics and master data of advanced planning
Topic 5
  • Explain and compare the different production methods in make-to-order
  • Determine BOM item category, describe order status management and set user statuses
Topic 6
  • Identify and explain production relevant master data
  • Outline best practices for using SAP S/4HANA
Topic 7
  • Material Requirements Planning in SAP S/4HANA
  • Describe its main components, the lines of business, and the SAP User Experience strategy
Topic 8
  • Describe the SAP HANA database concept and new user experience with SAP Fiori
  • Explain line load planning and confirmation, outline Kanban master data and Kanban processes
Topic 9
  • Outline both motivation and background of SAP S/4HANA
  • Detailed scheduling planning board) and advanced planning

 

NEW QUESTION 14
How can you set up the supply source for the SAP Kanban process? Note: There are 3correct answers to this question.

  • A. Using run schedule quantities for in-house production
  • B. Using stock transfer reservations for stock transfer
  • C. Using purchasing costs for automated source prioritization
  • D. Using quotations for internal and external procurement
  • E. Using purchase orders for external procurement

Answer: A,B,E

 

NEW QUESTION 15
What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?

  • A. The planned order generates capacity requirements.
  • B. The planned order is converted to a production order.
  • C. The planned order's components are copied from the picking list.
  • D. The planned order's component availability is checked

Answer: A

 

NEW QUESTION 16
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network? Note: There are
3 correct answers to this question.

  • A. SAP Concur
  • B. SAP Ariba
  • C. SAP Field glass
  • D. SAP C/4HANA
  • E. SAP SuccessFactors

Answer: A,B,C

 

NEW QUESTION 17
Which master data object governs the relationship between supply source and demand source in the Kanban process?

  • A. Replenishment strategy
  • B. Control cycle
  • C. Production supply area
  • D. Rate routing

Answer: B

 

NEW QUESTION 18
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.

  • A. Co-products
  • B. Waste products
  • C. Continuous flow materials
  • D. Bulk materials
  • E. By-products

Answer: A,B,E

 

NEW QUESTION 19
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

  • A. Move time
  • B. Wait time
  • C. Float before production
  • D. Pick/pack time
  • E. Queue time

Answer: B,D,E

 

NEW QUESTION 20
What does forecasting in the demand planning cycle include? Note: There are 3 correct answers to this question.

  • A. Past quotation quantities
  • B. Past procurement quantities
  • C. One-off events
  • D. Past sales order quantities
  • E. Market intelligence

Answer: C,D,E

 

NEW QUESTION 21
In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

  • A. Planning mode (bucket/sequence)
  • B. Direction (forward/backward)
  • C. Fixed pegging (on/off)
  • D. Finiteness level (0...1)
  • E. Scheduling control (finite/infinite)

Answer: A,B,E

 

NEW QUESTION 22
A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?

  • A. Change the item category of the phantom assembly in the BOM.
  • B. Change the phantom item indicator for the phantom assembly in the BOM.
  • C. Change the special procurement key of the phantom assembly in the BOM.
  • D. Change the explosion type of the phantom assembly in the BOM.

Answer: D

 

NEW QUESTION 23
Which bill of material (BOM) categories can you define in SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Functional Location BOM
  • B. Work Center BOM
  • C. Sales Order BOM
  • D. Class BOM

Answer: A,C

 

NEW QUESTION 24
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?

  • A. Use a planning group.
  • B. Use a propagation range.
  • C. Use a resource group.
  • D. Use a heuristic.

Answer: D

 

NEW QUESTION 25
What does the industry sector determine? Note: There are 2 correct answers to this question.

  • A. Whether material numbers are assigned internally or externally
  • B. Whether a material master fieldis required, changeable, displayed, or hidden
  • C. Which transaction you can use to create a new material
  • D. Which material master views can be maintained

Answer: B,D

 

NEW QUESTION 26
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.

  • A. In-house production time
  • B. Planned delivery time
  • C. Total replenishment lead time
  • D. Operation duration

Answer: A,B

 

NEW QUESTION 27
Which actions does the system perform by default when you save aconfirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

  • A. Material staging for next order in sequence
  • B. Posting of goods receipt for the product
  • C. Posting of production costs to the production cost collector
  • D. Archiving of documents for assembly scrap
  • E. Reduction of associated capacity requirements

Answer: B,C,E

 

NEW QUESTION 28
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers tothis question.

  • A. Predefined GMP compliant process order types to meet audit requirements
  • B. Documentation of quality data with Quality Management
  • C. Recipe approval (with Engineering Change Management)
  • D. Use of the digital signature function to check and run business processes
  • E. Use of the GMP compliant flag in relevant master data applications

Answer: B,C,D

 

NEW QUESTION 29
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?

  • A. Specify a positive offset time in the strategy profile.
  • B. Specify a negative offset time in the strategy profile.
  • C. Specify a positive planning horizon in the strategy profile.
  • D. Specify a negative planning horizon in the strategy profile.

Answer: B

 

NEW QUESTION 30
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

  • A. The work center has several individual capacities.
  • B. The Change Planning Direct on indicator is set.
  • C. Alternative resources are fully occupied.
  • D. The planning strategy is infinite.

Answer: A,D

 

NEW QUESTION 31
In your project,you have several materials that are planned by different people. How can you assign the planning responsibility?

  • A. MRP planning file
  • B. MRP type
  • C. MRP group
  • D. MRP controller

Answer: D

 

NEW QUESTION 32
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?

  • A. When you create a sales order
  • B. When you deliver a sales order
  • C. When the MRP results are saved
  • D. When you create a planned order

Answer: A

 

NEW QUESTION 33
What do you use to schedule operations from planned orders so that the production plan can be fulfilled?

  • A. Supply Network Planning (SNP)
  • B. Capacity Requirements Planning (CRP)
  • C. Material Requirements Planning (MRP)
  • D. Demand Planning (DP)

Answer: C

 

NEW QUESTION 34
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. By material type
  • B. By period
  • C. By industry
  • D. By plant

Answer: B,D

 

NEW QUESTION 35
......


SAP S/4HANA Production Planning and Manufacturing Certification Exam Details:

Exam NameSAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
Exam CodeC_TS422_2020
Duration180 mins
Passing ScoreC_TS422_2020 - 56%
C_TS422_1909 - 55%
Number of Questions80
Reference BooksTS421, TS422 (SAP S/4HANA 2020)
TS421 (SAP S/4HANA 1909), TS422 (SAP S/4HANA 1909)
Exam Price$550 (USD)
Schedule ExamSAP Training
LevelAssociate
Sample QuestionsSAP S/4HANA Production Planning and Manufacturing Certification Sample Questions

 

Free SAP Certified Application Associate C_TS422_2020 Exam Question: https://www.guidetorrent.com/C_TS422_2020-pdf-free-download.html