
Pass SAP C-TS422-2021 Exam Quickly With GuideTorrent
Prepare C-TS422-2021 Question Answers - C-TS422-2021 Exam Dumps
C-TS422-2021 Exam Certification Details:
| Level: | Associate |
| Exam: | 80 questions |
| Duration: | 180 mins |
| Sample Questions: | SAP C-TS422-2021 Exam Sample Question |
NEW QUESTION 35
What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?
- A. Supply Network Planning (SNP)
- B. Capacity Requirements Planning (CRP)
- C. Material Requirements Planning (MRP)
- D. Demand Planning (DP)
Answer: C
NEW QUESTION 36
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
- A. Work center
- B. Production version
- C. Plant
- D. Material
Answer: A,D
NEW QUESTION 37
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?
- A. When multiple operations are maintained for one product
- B. When multiple production versions are maintained for one product
- C. When alternate resources are used within one operation
- D. When multiple planned orders exist on one resource
Answer: C
NEW QUESTION 38
What are some uses for the low-level code assigned to each material?
- A. it is used by ATP to determine the priority of alternative components.
- B. It is used by product costing to determine how coast are rolled up.
- C. It is used in MRP to determine the sequence in which materials are planned.
- D. It is used by engineering to indentify subitems in an engineering bill of material (BOM).
Answer: B,C
NEW QUESTION 39
Why would you use phantom assemblies?
- A. To reduce the number of changes required in bills of materials
- B. To reduce the number of material masters
- C. To simplify the structure of bills of materials
- D. To increase the number of planning levels
- E. To make the assignment of components easier
Answer: A,C,E
NEW QUESTION 40
What is the difference between co-products and by-products?
- A. Only co-products can be manufactured in isolation from the main product.
- B. Only co-products appear in the process or production order settlement rule.
- C. Only co-products are identified by a special item category in the bill of material (BOM).
- D. Only by-products have a zero inventory valuation.
Answer: B
NEW QUESTION 41
Which standard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Work item
- B. Non-stock item
- C. Variable-size item
- D. WBS item
Answer: B,C
NEW QUESTION 42
What does forecasting in demand planning cycle include?
- A. Market intelligence
- B. Past quotation quantities
- C. Past sales order quantites
- D. Past procurment quantities
- E. One-off events
Answer: A,C,E
NEW QUESTION 43
Which mhetods are available for goods issue posting of material components for process orders?
- A. Transfer order
- B. Blackflushing
- C. Picking list
- D. Kanban
Answer: B,C
NEW QUESTION 44
What is a work center hierarchy in planning in SAP S/4HANA?
- A. A group of work centers in a parallel sequence that is used to split production quantities and work on them in parallel
- B. A group of work centers in a production line being used in sequence for production
- C. A group of alternative work centers for production, structured in hierarchy levels by priorities
- D. A group of alternative work centers providing a cumulative available capacity for production.
Answer: D
NEW QUESTION 45
What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?
- A. The work center has several invidula capacities.
- B. The finite Scheduling indicator is NOT set in the strategy profile.
- C. The Change Planning Direction indicator is set in strategy profile.
- D. Alternative work centers are fully occupied.
Answer: A,B
NEW QUESTION 46
What type of time element can be reduced by strategy settings while dispatching?
- A. Queue time
- B. Transportation time
- C. Setup time
- D. Wait time
Answer: A,D
NEW QUESTION 47
Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?
- A. Reduction of associated capacity requirements
- B. Archiving of documents for assembly scrap
- C. Posting of production costs to the production cost collector
- D. Material staging for nex order in sequence
- E. Posting of goods receipt for the product
Answer: A,C,E
NEW QUESTION 48
For what production type are production orders used?
- A. Replenishment controlled by control cycles
- B. Period and quantity-oriented production
- C. Process manufacturing processes
- D. Discrete manufacturing processes
Answer: D
NEW QUESTION 49
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?
- A. Fill up to the reorder stock level
- B. Fill up to the safety stoc level
- C. Fill up to the maximum stock level
- D. Fill up based on the lot size procedure
Answer: D
NEW QUESTION 50
You are working with planning strategy 40 (Planning-with-final assembly) When does consuption of planned independent requirements take places?
- A. When you deliver a sales order
- B. When the MRP result are saved
- C. When you create a sales order
- D. When you create a planned order
Answer: C
NEW QUESTION 51
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?
- A. SAP Concur
- B. SAP Fieldglass
- C. SAP Ariba
- D. SAP Hybris
- E. SAP SuccessFactors
Answer: A,B,C
NEW QUESTION 52
You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?
- A. Specify a negative offset time in the strategy profile.
- B. Specify a positive planning horizon in the strategy profile.
- C. Specify a negative lanning horizon in the strategy profile.
- D. Specify a positive offset time in the strategy profile.
Answer: A
NEW QUESTION 53
What happens to this dependent requirement when you convert the planned order into a production order?
- A. They are converted into a reservation.
- B. They are converted into a schedule line.
- C. They are converted into a production order.
- D. They are converted into a planned order.
Answer: A
NEW QUESTION 54
......
Real SAP C-TS422-2021 Exam Questions [Updated 2023]: https://www.guidetorrent.com/C-TS422-2021-pdf-free-download.html
Free C-TS422-2021 Exam Dumps to Pass Exam Easily: https://drive.google.com/open?id=1EuY6_-MnwamsKlQFxrB79FhugC6w3s36