[Jan-2022] AACE-PSP Certification with Actual Questions from GuideTorrent Updated AACE-PSP Dumps PDF - AACE-PSP Real Valid Brain Dumps With 120 Questions! How to book the Planning & Scheduling Professional (PSP) Exam Follow the steps mentioned below to book the Planning Scheduling Professional (PSP) Exam: Step 1: Visit the AACE's website by clicking hereStep 2: Create a new account or log in to an [...]

[Jan-2022] AACE-PSP Certification with Actual Questions from GuideTorrent [Q17-Q37]

Share

[Jan-2022] AACE-PSP Certification with Actual Questions from GuideTorrent

Updated AACE-PSP Dumps PDF - AACE-PSP Real Valid Brain Dumps With 120 Questions!


How to book the Planning & Scheduling Professional (PSP) Exam

Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:

  • Step 1: Visit the AACE's website by clicking here
  • Step 2: Create a new account or log in to an existing account
  • Step 3: Select your professional exam
  • Step 4: Complete the required course and take PSP practice test
  • Step 5: Fill the application and submit all required documents
  • Step 6: Schedule your exam by following the instructions on the website

For more info read reference:

Official Website

Exam Contents

FAQs and Guide

 

NEW QUESTION 17
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inadequate definition of scope at the estimate (budget) stage
  • B. Insufficient planning for change management
  • C. lack of detailed planning for operational start-up
  • D. Inappropriate definition of work breakdown structure

Answer: A

 

NEW QUESTION 18
Budgeted cost of work scheduled is _______________________.

  • A. The expected total cost of an activity, group of activities or the project
  • B. The sum of all budgets for work scheduled to be accomplished within a given time period
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The total authorized budget for accomplishing the project scope

Answer: A

 

NEW QUESTION 19
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Remaining duration of activities.
  • B. Actual finish of activities.
  • C. Percent complete.
  • D. Original duration of activities.

Answer: A

 

NEW QUESTION 20
Which of the following is NOT true?

  • A. Remaining durations can exceed original durations.
  • B. A network must contain only one Critical Path.
  • C. Multiple calendars can affect the total float calculation.
  • D. Constraints can interfere with the longest path calculation.

Answer: A

 

NEW QUESTION 21
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-11-02.
  • B. 06-04-02.
  • C. 06-18-02.
  • D. 06-05-02.

Answer: D

 

NEW QUESTION 22
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

  • A. PDM is a bar chart with network logic, while ADM is a pure logic network.
  • B. ADM is manual CPM calculations, while PDM is computerized.
  • C. ADM uses arrows, while PDM uses boxes.
  • D. ADM is limited to finish-to-start logic relationships, while PDM is not.

Answer: D

 

NEW QUESTION 23
What owner action could have mitigated the late completion of the project?

  • A. Self-perform more of the work.
  • B. Hire a more senior project manager.
  • C. Prepare better structural steel drawings.
  • D. Use a procurement agent to monitor and expedite equipment deliveries.

Answer: D

 

NEW QUESTION 24
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. B.
  • B. W.
  • C. S.
  • D. C.

Answer: C

 

NEW QUESTION 25
What is the workweek period for this project?

  • A. Monday through Friday
  • B. Monday through Saturday
  • C. Sunday through Friday
  • D. Sunday through Saturday

Answer: D

 

NEW QUESTION 26
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

  • A. 168 days
  • B. 193 days
  • C. 91 days
  • D. 183 days

Answer: D

 

NEW QUESTION 27
What is the actual duration as of the status date or data date of Activity B?

  • A. 4.
  • B. 0.
  • C. 7.
  • D. 3.

Answer: D

 

NEW QUESTION 28
At a minimum, periodic reporting must be done at what interval?

  • A. Monthly.
  • B. As requested by the owner.
  • C. As requested by the project manager.
  • D. As specified in the contract documents.

Answer: D

 

NEW QUESTION 29
What was the original planned duration for Activity A through Activity G?

  • A. 25.
  • B. 26.
  • C. 28.
  • D. 24.

Answer: C

 

NEW QUESTION 30
What is a key first step in developing a critical path method schedule?

  • A. Defining the execution plan to meet the required scope of work.
  • B. Setting out the resource to be used and its limitations.
  • C. Drawing the logic diagram.
  • D. Drawing a bar chart of the key phrases of the work.

Answer: C

 

NEW QUESTION 31
For which of these delays should an owner grant a time extension?

  • A. Shop drawings and centrifuge delay.
  • B. Differing site conditions and centrifuge delay.
  • C. Structural steel shop drawings.
  • D. Differing site conditions at parking structure.

Answer: D

 

NEW QUESTION 32
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. Yes, by 9 calendar days.
  • B. Yes, by 14 calendar days.
  • C. NO.
  • D. Yes, by 4 calendar days.

Answer: D

 

NEW QUESTION 33
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 267 days
  • B. 255 days
  • C. 362 days
  • D. 407 days

Answer: D

 

NEW QUESTION 34
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

  • A. 24 lifts
  • B. 30 lifts
  • C. 48 lifts
  • D. 36 lifts

Answer: D

 

NEW QUESTION 35
Each of the following accurately describes total float in a schedule EXCEPT:

  • A. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
  • B. The amount of time an activity can be delayed without delaying the overall project completion time.
  • C. Can be positive or negative.
  • D. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.

Answer: A

 

NEW QUESTION 36
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

  • A. Estimate at completion (EAC)
  • B. Estimate to complete (ETC)
  • C. Budgeted cost of work performed (BCWP)
  • D. Budget at completion (BAC)

Answer: B

 