Pass PRINCE2 PRINCE2-Agile-Practitioner Exam with Guarantee Updated 50 Questions Latest PRINCE2-Agile-Practitioner Pass Guaranteed Exam Dumps Certification Sample Questions PRINCE2 PRINCE2-Agile-Practitioner Exam Syllabus Topics: TopicDetailsTopic 1Certification Validity: This section informs candidates about the certification's validity period, which is three years for PRINCE2 Agile Practitioner holders. [...]

Pass PRINCE2 PRINCE2-Agile-Practitioner Exam with Guarantee Updated 50 Questions [Q17-Q33]

Share

Pass PRINCE2 PRINCE2-Agile-Practitioner Exam with Guarantee Updated 50 Questions

Latest PRINCE2-Agile-Practitioner Pass Guaranteed Exam Dumps Certification Sample Questions


PRINCE2 PRINCE2-Agile-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • Certification Validity: This section informs candidates about the certification's validity period, which is three years for PRINCE2 Agile Practitioner holders. The emphasis is on maintaining certification through either re-sitting the exam or engaging in AXELOS membership activities.
Topic 2
  • Target Audience: This domain is designed for professionals working in project environments, particularly those responsible for integrating project management with product delivery. It outlines the certification's relevance for individuals looking to enhance their project management capabilities while maintaining governance and control.
Topic 3
  • PRINCE2 AgileĀ® Practitioner Overview: This section of the exam measures the skills of PRINCE2 Project Managers and covers the integration of PRINCE2 and Agile methodologies. Candidates will learn how to effectively combine these approaches to create a comprehensive project management solution that balances control with flexibility.
Topic 4
  • Skills and Processes: This section measures the capabilities of PRINCE2 Project Managers in utilizing best practice guidance for project delivery. It focuses on equipping professionals with the necessary skills to manage projects effectively in fast-paced environments.
Topic 5
  • Project Management Solution: This domain is aimed at PRINCE2 Agile Practitioners and highlights the importance of a complete project management solution. It emphasizes the synergy between agile flexibility and the structured framework of PRINCE2.

 

NEW QUESTION # 17
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team have noted in their daily stand-up that they cannot work out the versions and review status of the information and photos which will appear on the website pages.
Which core practice might be the MOST useful to immediately help with the 'managing product delivery' process?

  • A. Identify the effect of delaying the delivery of a web page in a daily stand-up.
  • B. Visualize the status of the work using a 'ticket' board with 'swim lanes'.
  • C. Refer to a cumulative flow diagram to identify the status of the remaining work.
  • D. Carry out a safe-to-fail experiment to identify a better way of working.

Answer: B

Explanation:
Using a 'ticket' board with 'swim lanes' allows the Marketing Team to visualize the different versions and review statuses of the information and photos for the website. This practice helps clarify the current state of work, promotes transparency, and facilitates better communication within the team, ultimately supporting effective management of product delivery.


NEW QUESTION # 18
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
In order to assess the prevailing agile environment, the project manager made use of the Agilometer. A summary of the results from canvassing the views of key stakeholders involved in the Event Village is provided below:
Slider
Flexibility on what is delivered:Score 5
Level of Collaboration:Score 2
Ease of Communication:Score 3
Ability to work iteratively and deliver incrementally:Score 4
Advantageous Environmental Conditions:Score 5
Acceptance of Agile:Score 3
Which observation is appropriate at this point?

  • A. The average score supports adopting Agile behaviours, concepts and techniques.
  • B. There is a need to investigate if team members have been disappointed by working in teams before.
  • C. There is a need to evolve the Agilometer to better suit the needs of the project manager.
  • D. There are likely to be too many requirements that are 'Musts Haves' to be able to use PRINCE2 Agile.

Answer: A

Explanation:
The scores indicate a mixed but generally positive view of the agile environment, with certain areas like flexibility and advantageous conditions scoring well. While collaboration and communication could improve, the overall results suggest that there is a foundation for adopting Agile behaviors, concepts, and techniques within the project. This supports the notion of continuing with agile practices while focusing on areas that need enhancement.


NEW QUESTION # 19
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team has created a plan of 9 timeboxes that always end on a Friday. The senior user has decided to visit the Marketing Team every Friday in order to attend their regular reviews.
Which reason BEST explains whether this is a suitable approach for the 'directing a project' process?

  • A. It is a poor approach because the senior user should focus on looking at the information radiator instead.
  • B. It is a good approach because the senior user will be able to oversee the performance of the team.
  • C. It is a poor approach because the reviews should be scheduled as needed, when products are developed.
  • D. It is a good approach because regular reviews will provide rich information to assess project viability.

Answer: D

Explanation:
Regular reviews conducted by the senior user allow for continuous assessment of the project's progress, ensuring that the project remains aligned with its objectives and can adapt to any necessary changes. This ongoing engagement is vital for maintaining project viability and stakeholder involvement.


NEW QUESTION # 20
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
Just before the event the team finds out that a major football match is taking place during the tournament and that many people will want to see it. One solution is to hire a large TV screen to display the game in the Event Village. However, the biggest concern is that the cheapest supplier has many mandatory requirements for access, technical elements and work conditions in their contract.
If the agile environment for the project was reassessed, should the 'Advantageous Environmental Conditions' slider on the Agilometer be increased?

  • A. It should be reduced because the TV screen hire company is NOT supportive to working in an agile way.
  • B. It should be reduced because the TV screen would increase the 'ease of communication' slider instead.
  • C. It should be increased because the Event Village team is being 'change friendly' in organizing the TV screen.
  • D. It should be increased because high-value contracts should be designed to reduce the risk.

Answer: A

Explanation:
If the supplier has many mandatory requirements for access, technical elements, and work conditions that may hinder flexibility and responsiveness, it suggests that the conditions are not conducive to an agile environment. This lack of support for agile principles would warrant a reduction in the 'Advantageous Environmental Conditions' slider on the Agilometer.


NEW QUESTION # 21
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Apps and Social Media work package includes the following requirements:
1. Fitness app - Must Have
2. Healthy eating app - Should Have
The burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.
The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.
What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?

  • A. It applies the principle poorly because the Website Team should be empowered to deal with issues relating to the work package.
  • B. It applies the principle well because the project manager will now decide how to proceed with the issue.
  • C. It applies the principle well because the project manager's decision helps the Website Team self- organize within the constraints of the work package.
  • D. It applies the principle poorly because everyone in the Website Team should be aware that the work package is outside of tolerance.

Answer: A

Explanation:
By removing the burn-down chart from the information radiator, the project manager limits the team's ability to visualize and manage their progress and challenges. In PRINCE2 Agile, teams should be empowered to handle issues within their work package, and transparency through tools like the burn-down chart is essential for self-management and collaboration.


NEW QUESTION # 22
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team is not sure whether all the information, photos and links needed for the website pages being set up by the Website Team can be delivered within the current timebox.
One of the team members has suggested that the team regularly visit the LGA's cafeteria to show the staff in other departments some rough drawings of the website pages to get their feedback. This can then be used to help decide which parts of each page are most important to deliver within the timebox.
Which BEST explains how this approach manages change?

  • A. It is a good approach because changes at the high level for a timebox will NOT affect the baseline.
  • B. It is a good approach because changes to the website information should be based on feedback.
  • C. It is a poor approach because some of the website pages should be moved to the next timebox.
  • D. It is a poor approach because exploration is a behaviour that requires a creative environment to enable change.

Answer: B

Explanation:
By seeking feedback from staff on rough drawings of the website pages, the Marketing Team can make informed decisions about what content is most valuable and should be prioritized for delivery within the current timebox. This responsive approach allows the team to adapt to feedback effectively, ensuring the final product meets stakeholder needs.


NEW QUESTION # 23
Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile?

  • A. Reducing quality testing in order to deliver within agreed deadlines.
  • B. Providing guidance on tailoring any applicable principles, themes and processes.
  • C. Encouraging system improvement through visualization and controlling work in progress.
  • D. Favoring processes and tools over individuals and interactions.

Answer: C

Explanation:
This approach aligns with Agile principles, emphasizing continuous improvement and effective workflow management, which can complement the structured framework of PRINCE2 Agile.


NEW QUESTION # 24
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager has agreed with the Website team manager delivering the Social Media work package that the team should try using the Kanban method along with their existing Scrum approach to improve delivery.
The team is now going to use a Kanban board as part of their information radiator.
Which explains the additional benefit of combining these two agile approaches during the 'managing product delivery' process?

  • A. By using Kanban, collaborative working is enabled between members of the Website Team delivering the social media.
  • B. Using Kanban limits the amount of work being carried out by the team, with the aim of improving delivery during the sprint.
  • C. A Kanban board makes the status of the Social Media work package visible to the delivery team.
  • D. Using Kanban limits the amount of scope change on the project and therefore increases velocity.

Answer: C

Explanation:
A Kanban board provides a visual representation of the workflow, making it easy for the team to see the status of tasks within the Social Media work package. This increased visibility helps the team manage their work more effectively, identify bottlenecks, and facilitate communication, enhancing overall productivity and coordination during the delivery process.


NEW QUESTION # 25
Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?

  • A. To allow teams to self-organize whilst staying in control.
  • B. To adjust a 'command and control' culture for product delivery.
  • C. Projects should be established with the intention of NOT delivering everything.
  • D. PRINCE2 Agile is NOT a substitute for PRINCE2.

Answer: A

Explanation:
This approach enables teams to adopt Agile practices while maintaining the governance and structure provided by PRINCE2, promoting both flexibility and control in project delivery.


NEW QUESTION # 26
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager is creating the stage plan for Stage 3. The project manager is trying to incorporate the Team Registration work package into the stage plan.
How should the stage plan be produced?

  • A. By the project manager, after discussing which website user stories should be delivered.
  • B. Using rationalism to estimate the effort to deliver the website sprints during the stage.
  • C. By pulling website tasks from the backlog dynamically into the work package as soon as there is capacity.
  • D. Using the velocity from the previous stage, working together with the Scrum Master and team members.

Answer: D

Explanation:
Utilizing the velocity from the previous stage provides a data-driven basis for estimating how much work can be accomplished in the upcoming stage. Collaborating with the Scrum Master and team members ensures that the plan is realistic and aligns with the team's capabilities, facilitating effective planning and execution of the Team Registration work package.


NEW QUESTION # 27
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
A requirement for the changing room facilities in the Event Village has been defined as a technical story as follows:
'Changing room facilities should have water pressure between 1.5 - 3 bar and must have a water pressure of at least between 0.1 - 0.5 bar.' Has this requirement been recorded correctly?

  • A. Yes, because non-functional requirements may apply to more than one user story.
  • B. No, because non-functional requirements should only be documented as quality criteria.
  • C. No, because non-functional requirements should always be part of the user stories.
  • D. Yes, because a product's performance range should only appear as a technical story.

Answer: C

Explanation:
Non-functional requirements, such as performance criteria (in this case, water pressure), should typically be included as part of the user stories to ensure they are considered in the context of the overall functionality and user experience. This integration helps maintain a holistic view of what the system should deliver, ensuring that both functional and non-functional aspects are addressed together.


NEW QUESTION # 28
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

  • A. It applies the target poorly because the CSME should have been added during Stage 2 to improve progress.
  • B. It applies the target poorly because the LGA will NOT have access to the health and safety expert during Stage 3.
  • C. It applies the target well because the team manager should remove obstacles to delivery.
  • D. staff members are able to give advice on health and fitness.
    This is covered by four work packages:
    1. Training syllabus:
    * High-level design of the manual.
    * Content of each module.
    2. Course content for safety and professionalism:
    * Detailed design of two modules:
    * Health and Safety including basic first aid.
    * Customer relations to look after people attending the event.
    * Piloting the modules with a group of volunteers.
    3. Course content tor giving advice on health and fitness:
    * Detailed design of two modules:
    * Exercise fundamentals including how to warm up and cool down.
    * Healthy eating including what types of food are good for you.
    * Piloting the modules with a group of volunteers.
    4. Training delivery:
    * Production of the training manual;
    * Delivery of the training to the rest of the volunteers.
    The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
    Using the Project Scenario and Staff Training Additional information, answer the following question:
    The LGA's social media expert has advised that a few social media channels already used by the LGA have much more traffic than many of the others that are available.
    However, the customer subject matter expert has requested a presence on a wide range of social media channels to promote the health and fitness messages.
    Which reason explains why the team manager should focus delivery on the most popular social media channels according to the five targets?
  • E. It applies the target well because the relevant skills should be available for each timebox.
  • F. the event is carried out safely and professionally;

Answer: E

Explanation:
Concentrating on the most popular social media channels maximizes the potential reach and engagement for the health and fitness messages. By prioritizing these channels, the team can effectively promote discussions and interactions, aligning with the goal of generating awareness and interest in the initiative while utilizing resources efficiently.


NEW QUESTION # 29
What does PRINCE2 Agile identify as a 'concept'?

  • A. Trusting and not blaming others.
  • B. Using daily stand-up meetings and user stories.
  • C. Prioritizing what needs to be delivered.
  • D. Setting tolerances for each project objective to establish limits of authority.

Answer: B

Explanation:
This option reflects key practices in Agile methodologies, emphasizing collaboration and iterative progress, which are central to Agile principles.


NEW QUESTION # 30
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

  • A. The training must be delivered so that the volunteers understand the health and safety requirements.
  • B. The health and safety training should be left out if it cannot be delivered before the football tournament.
  • C. The volunteers will take time to understand the training before they can apply it safely.
  • D. The health and safety training must be delivered before the planned football tournament takes place.
  • E. staff members are able to give advice on health and fitness.
    This is covered by four work packages:
    1. Training syllabus:
    * High-level design of the manual.
    * Content of each module.
    2. Course content for safety and professionalism:
    * Detailed design of two modules:
    * Health and Safety including basic first aid.
    * Customer relations to look after people attending the event.
    * Piloting the modules with a group of volunteers.
    3. Course content tor giving advice on health and fitness:
    * Detailed design of two modules:
    * Exercise fundamentals including how to warm up and cool down.
    * Healthy eating including what types of food are good for you.
    * Piloting the modules with a group of volunteers.
    4. Training delivery:
    * Production of the training manual;
    * Delivery of the training to the rest of the volunteers.
    The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
    Using the Project Scenario and Staff Training Additional information, answer the following question:
    The Staff Training Team have developed the following user story:
    'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target?
  • F. the event is carried out safely and professionally;

Answer: E

Explanation:
Timely delivery of the health and safety training is crucial to ensure that all volunteers are adequately prepared before the event. Meeting this deadline is essential for ensuring a safe environment for the public during the football tournament, making it a priority to adhere to the schedule.


NEW QUESTION # 31
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The project manager recommends that Stage 2 should be broken down further with more stage boundaries linked to the weekly publication of a newspaper advertisement.
Using the Timeline, which statement BEST evaluates this proposal in relation to the 'manage by stages' principle?

  • A. It applies the principle poorly because stage boundaries should be set at the beginning of each new timebox.
  • B. It applies the principle well because short stage boundaries provide more opportunity for inter-team collaboration.
  • C. It applies the principle poorly because the stage boundaries should typically be monthly on a three- month project.
  • D. It applies the principle well because short stage boundaries will enable the project to fail-fast and learn- fast.

Answer: D

Explanation:
The 'manage by stages' principle emphasizes breaking the project into manageable stages to assess progress and adapt as necessary. By creating shorter stage boundaries linked to the weekly publication of advertisements, the project can quickly identify issues and adjust strategies, fostering a learn-fast approach.


NEW QUESTION # 32
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:

  • A. staff members are able to give advice on health and fitness.
    This is covered by four work packages:
    1. Training syllabus:
    * High-level design of the manual.
    * Content of each module.
    2. Course content for safety and professionalism:
    * Detailed design of two modules:
    * Health and Safety including basic first aid.
    * Customer relations to look after people attending the event.
    * Piloting the modules with a group of volunteers.
    3. Course content tor giving advice on health and fitness:
    * Detailed design of two modules:
    * Exercise fundamentals including how to warm up and cool down.
    * Healthy eating including what types of food are good for you.
    * Piloting the modules with a group of volunteers.
    4. Training delivery:
    * Production of the training manual;
    * Delivery of the training to the rest of the volunteers.
    The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
    Using the Project Scenario and Staff Training Additional information, answer the following question:
    The project product description for the sports event includes the following acceptance criteria (AC):
    * It must be possible for the training materials to be maintained in the future by the LGA training department.
    * The training materials must be usable for future events run by the LGA.
    Which reason explains why the team manager should protect the level of quality in relation to the acceptance criteria?
  • B. The AC should be tested using spikes to trial the maintenance procedures.
  • C. The AC should be made transparent for maintenance by the training department.
  • D. The AC should be met so that the cost of ownership of the materials is acceptable.
  • E. The AC should be delivered as a minimum viable product.
  • F. the event is carried out safely and professionally;

Answer: E

Explanation:
Ensuring that the acceptance criteria are met is crucial for maintaining the quality of the training materials.
This not only affects the usability for future events but also impacts the long-term cost of ownership, as high- quality materials will require less maintenance and adaptation over time. Protecting quality helps ensure that the investment in the training materials is justified and sustainable for future use.


NEW QUESTION # 33
......

New PRINCE2-Agile-Practitioner Test Materials & Valid PRINCE2-Agile-Practitioner Test Engine: https://www.guidetorrent.com/PRINCE2-Agile-Practitioner-pdf-free-download.html

PRINCE2-Agile-Practitioner Updated Exam Dumps [2025] Practice Valid Exam Dumps Question: https://drive.google.com/open?id=1VPCEOpHPoqGVJgrGHrsKY2Uu_Hw1j958